What is the difference between Sprint and Iteration in Scrum and length of each Sprint? [closed]

  1. Is there a difference between Sprint and an Iteration or one can have Iterations within a Sprint or Sprint is just the terminology used instead of Iteration in Scrum? It will be helpful if someone can throw some light on this.

  2. Suppose there are 4 sprints and you have decided the first sprint will go up to 10 days is it required that other 3 sprints should have the same length of the 1st decided sprint's length??.

like image 883
kurozakura Avatar asked Aug 04 '09 12:08

kurozakura


People also ask

What is the difference between sprint and iteration in Scrum?

Sprints are more focused on productivity techniques developed by a group of individuals working on the same project. Iterations describe a development and planning process where a project is developed in small sections.

Is an iteration the same as a sprint?

Sprint and iteration are essentially the same things. The standard duration for each is two weeks. However, on rare occasions, the work context may make a one, two, three, or four-week iteration a better choice.

What is the length of a Scrum sprint?

And how long is a sprint in Agile? Sprints in scrum can be as long as you want; however, it's most common for sprint length to be between 1 and 4 weeks.

How many day iteration is called a sprint?

Sprint vs iteration: Exploring both terms Usually, sprints last about seven days or so. As a team, the end goal is to “sprint” or quickly reach, the desired goal.


1 Answers

All sprints are iterations but not all iterations are sprints. Iteration is a common term in iterative and incremental development (IID). Scrum is one specialized flavor of IID so it makes sense to specialize the terminology as well. It also helps brand the methodology different from other IID methodologies :)

As to the sprint length: anything goes as long as the sprint is timeboxed i.e. it is finished on the planned date and not "when it's ready". (Or alternatively, in rare occasions, the sprint is terminated prematurely to start a new sprint in case some essential boundary conditions are changed.)

It does help to have the sprints of similar durations. There's less to remember about the sprint schedule and your planning gets more accurate. I like to keep mine at 2 calendar weeks, which will resolve into 8..10 business days outside holiday seasons.

like image 158
laalto Avatar answered Oct 14 '22 03:10

laalto