I've just finished up with a prototype implementation of a supervised learning algorithm, automatically assigning categorical tags to all the items in our company database (roughly 5 million items).
The results look good, and I've been given the go-ahead to plan the production implementation project.
I've done this kind of work before, so I know how the functional components of the software. I need a collection of web crawlers to fetch data. I need to extract features from the crawled documents. Those documents need to be segregated into a "training set" and a "classification set", and feature-vectors need to be extracted from each document. Those feature vectors are self-organized into clusters, and the clusters are passed through a series of rebalancing operations. Etc etc etc etc.
So I put together a plan, with about 30 unique development/deployment tasks, each with time estimates. The first stage of development -- ignoring some advanced features that we'd like to have in the long-term, but aren't high enough priority to make it into the development schedule yet -- is slated for about two months worth of work. (Keep in mind that I already have a working prototype, so the final implementation is significantly simpler than if the project was starting from scratch.)
My manager said the plan looked good to him, but he asked if I could reorganize the tasks into user stories, for a few reasons: (1) our project management software is totally organized around user stories; (2) all of our scheduling is based on fitting entire user stories into sprints, rather than individually scheduling tasks; (3) other teams -- like the web developers -- have made great use of agile methodologies, and they've benefited from modelling all the software features as user stories.
So I created a user story at the top level of the project:
As a user of the system, I want to search for items by category, so that I can easily find the most relevant items within a huge, complex database.
Or maybe a better top-level story for this feature would be:
As a content editor, I want to automatically create categorical designations for the items in our database, so that customers can easily find high-value data within our huge, complex database.
But that's not the real problem.
The tricky part, for me, is figuring out how to create subordinate user stories for the rest of the machine learning architecture.
Case in point... I know that the algorithm requires two major architectural subdivisions: (A) training, and (B) classification. And I know that the training portion of the architecture requires construction of a cluster-space.
All the Agile Development literature I've read seems to indicate that a user story should be the "smallest possible implementation that provides any business value". And that makes a lot of sense when designing a piece of end-user software. Start small, and then incrementally add value when users demand additional functionality.
But a cluster-space, in and of itself, provides zero business value. Nor does a crawler, or a feature-extractor. There's no business value (not for the end-user, or for any of the roles internal to the company) in a partial system. A trained cluster-space is only possible with the crawler and feature extractor, and only relevant if we also develop an accompanying classifier.
I suppose it would be possible to create user stories where the subordinate components of the system act as the users in the stories:
As a supervised-learning cluster-space construction routine, I want to consume data from a feature extractor, so that I can exist.
But that seems really weird. What benefit does it provide me as the developer (or our users, or any other stakeholders, for that matter) to model my user stories like that?
Although the main story can be easily divided along architectural-component boundaries (crawler, trainer, classifier, etc), I can't think of any useful decomposition from a user's perspective.
What do you guys think? How do you plan Agile user stories for sophisticated, indivisible, non-user-facing components?
The Machine Learning cycle is closely aligned with the Agile methodology. Agile was designed for situations that are very complex and non-static, and which we do not fully understand from the start. It provides a roadmap and a direction towards finding the answers, but it allows and encourages change.
There are a few important things to consider when breaking down user stories into tasks: Keep tasks small, but not too small. As a rule of thumb, a task should be something that can be done within a single day, but not in a few minutes' time either. Keep tasks very precise in scope.
It might be helpful to utilize the 'vertical slices' concept. Imagine a simple 3-layer application (UI/Logic/DB, for example). Instead of building out one layer, then another, you 'slice' vertically through all three. An initial story might be "As a user, I want to be able to log in to the system, so that I can access it." When done, this story is potentially-shippable, in that it provides complete functionality, but is highly unlikely to provide sufficient value to the customer to make it worth actually shipping. One benefit of vertical slices is that you've learned something about all the layers, knowledge which can be use in future iterations.
If you're not familiar with it, the INVEST model is very useful for User Stories:
I - Independent
N - Negotiable
V - Valuable
E - Estimable
S - Sized appropriately
T - Testable