What happens in Scrum when the development team is the support team as well? How can this be improved using Jira?
We can't have a fire fighter because not all developers can solve both front-end and back-end issues. But the support issues make team velocity difficult to obtain.
4) What happens if the Developers cannot complete its work by the end of the Sprint? The Developers inform the Product Owner. The Scrum Team should then inspect & adapt to prevent this in future if it is a problem. Understanding why this has happened will be critical.
During the Sprint execution, if the Development Team determines it has too much or too little work, or there are blockers/impediments blocking the progress of the Sprint, it may renegotiate the selected Product Backlog items with the Product Owner. It is extremely crucial to keep the Scrum/KANBAN board updated.
At the end of a sprint, if there is incomplete work: "All incomplete Product Backlog Items are re-estimated and put back on the Product Backlog." This does not have to mean that the sprint was unsuccessful, as per the Scrum Guide: "If the Development Team determines it has too much or too little work, it may ...
Mike Cohn wrote a good article on sprint planning for teams with a lot of interruptions.
He suggests having a rolling estimate of the average time spent on interruptions. Then allow for that when you do sprint planning.
For example, say the team averages 30% of their time spent on fixing issues. When you do the planning you plan for a capacity of 70% for development work.
As you mention in your question, nominating a person to handle issue fixes is a common approach. This is beneficial as it allows the other members of the team to focus on new development work without unexpected interruptions. In your situation where developers are specialists this is more difficult to achieve. You may want to consider doing some cross-skilling so that developers can handle a broader range of issues. They may not fix some issues as well as a specialist, but the loss in efficiency is gained back by the rest of the team avoiding interruptions.
Other things worth considering:
Production bugs have a bigger impact than the time spent fixing them due to the unpredictable way in which the work arises. That is why focusing on quality makes sense, even if it does seem like a lot of extra effort.
So the SCRUM is really for planned work, and if there is a lot of interruptions it may not be the best approach, maybe you should look at kanban or combination of both?