Logo Questions Linux Laravel Mysql Ubuntu Git Menu
 

Count work days between two dates

Tags:

date

sql

tsql

People also ask

Can Excel calculate working days between two dates?

The Excel NETWORKDAYS function calculates the number of working days between two dates. NETWORKDAYS automatically excludes weekends (Saturday and Sunday) and can optionally exclude a list of holidays supplied as dates.

Is there a way to calculate business days in Excel?

Then, to calculate the number of business days in the specified time period, type the formula =NETWORKDAYS(B3,B4), where B3 is the starting date and B4 is the ending date.

How do you calculate business days?

Business days are the weekdays Monday through Friday. Check Business Days Only to exclude weekend days in your calendar calculation. Check Saturday is a Business Day to include Saturdays. Holidays are not included in the calculation.


For workdays, Monday to Friday, you can do it with a single SELECT, like this:

DECLARE @StartDate DATETIME
DECLARE @EndDate DATETIME
SET @StartDate = '2008/10/01'
SET @EndDate = '2008/10/31'


SELECT
   (DATEDIFF(dd, @StartDate, @EndDate) + 1)
  -(DATEDIFF(wk, @StartDate, @EndDate) * 2)
  -(CASE WHEN DATENAME(dw, @StartDate) = 'Sunday' THEN 1 ELSE 0 END)
  -(CASE WHEN DATENAME(dw, @EndDate) = 'Saturday' THEN 1 ELSE 0 END)

If you want to include holidays, you have to work it out a bit...


In Calculating Work Days you can find a good article about this subject, but as you can see it is not that advanced.

--Changing current database to the Master database allows function to be shared by everyone.
USE MASTER
GO
--If the function already exists, drop it.
IF EXISTS
(
    SELECT *
    FROM dbo.SYSOBJECTS
    WHERE ID = OBJECT_ID(N'[dbo].[fn_WorkDays]')
    AND XType IN (N'FN', N'IF', N'TF')
)
DROP FUNCTION [dbo].[fn_WorkDays]
GO
 CREATE FUNCTION dbo.fn_WorkDays
--Presets
--Define the input parameters (OK if reversed by mistake).
(
    @StartDate DATETIME,
    @EndDate   DATETIME = NULL --@EndDate replaced by @StartDate when DEFAULTed
)

--Define the output data type.
RETURNS INT

AS
--Calculate the RETURN of the function.
BEGIN
    --Declare local variables
    --Temporarily holds @EndDate during date reversal.
    DECLARE @Swap DATETIME

    --If the Start Date is null, return a NULL and exit.
    IF @StartDate IS NULL
        RETURN NULL

    --If the End Date is null, populate with Start Date value so will have two dates (required by DATEDIFF below).
     IF @EndDate IS NULL
        SELECT @EndDate = @StartDate

    --Strip the time element from both dates (just to be safe) by converting to whole days and back to a date.
    --Usually faster than CONVERT.
    --0 is a date (01/01/1900 00:00:00.000)
     SELECT @StartDate = DATEADD(dd,DATEDIFF(dd,0,@StartDate), 0),
            @EndDate   = DATEADD(dd,DATEDIFF(dd,0,@EndDate)  , 0)

    --If the inputs are in the wrong order, reverse them.
     IF @StartDate > @EndDate
        SELECT @Swap      = @EndDate,
               @EndDate   = @StartDate,
               @StartDate = @Swap

    --Calculate and return the number of workdays using the input parameters.
    --This is the meat of the function.
    --This is really just one formula with a couple of parts that are listed on separate lines for documentation purposes.
     RETURN (
        SELECT
        --Start with total number of days including weekends
        (DATEDIFF(dd,@StartDate, @EndDate)+1)
        --Subtact 2 days for each full weekend
        -(DATEDIFF(wk,@StartDate, @EndDate)*2)
        --If StartDate is a Sunday, Subtract 1
        -(CASE WHEN DATENAME(dw, @StartDate) = 'Sunday'
            THEN 1
            ELSE 0
        END)
        --If EndDate is a Saturday, Subtract 1
        -(CASE WHEN DATENAME(dw, @EndDate) = 'Saturday'
            THEN 1
            ELSE 0
        END)
        )
    END
GO

If you need to use a custom calendar, you might need to add some checks and some parameters. Hopefully it will provide a good starting point.


All Credit to Bogdan Maxim & Peter Mortensen. This is their post, I just added holidays to the function (This assumes you have a table "tblHolidays" with a datetime field "HolDate".

--Changing current database to the Master database allows function to be shared by everyone.
USE MASTER
GO
--If the function already exists, drop it.
IF EXISTS
(
    SELECT *
    FROM dbo.SYSOBJECTS
    WHERE ID = OBJECT_ID(N'[dbo].[fn_WorkDays]')
    AND XType IN (N'FN', N'IF', N'TF')
)

DROP FUNCTION [dbo].[fn_WorkDays]
GO
 CREATE FUNCTION dbo.fn_WorkDays
--Presets
--Define the input parameters (OK if reversed by mistake).
(
    @StartDate DATETIME,
    @EndDate   DATETIME = NULL --@EndDate replaced by @StartDate when DEFAULTed
)

--Define the output data type.
RETURNS INT

AS
--Calculate the RETURN of the function.
BEGIN
    --Declare local variables
    --Temporarily holds @EndDate during date reversal.
    DECLARE @Swap DATETIME

    --If the Start Date is null, return a NULL and exit.
    IF @StartDate IS NULL
        RETURN NULL

    --If the End Date is null, populate with Start Date value so will have two dates (required by DATEDIFF below).
    IF @EndDate IS NULL
        SELECT @EndDate = @StartDate

    --Strip the time element from both dates (just to be safe) by converting to whole days and back to a date.
    --Usually faster than CONVERT.
    --0 is a date (01/01/1900 00:00:00.000)
    SELECT @StartDate = DATEADD(dd,DATEDIFF(dd,0,@StartDate), 0),
            @EndDate   = DATEADD(dd,DATEDIFF(dd,0,@EndDate)  , 0)

    --If the inputs are in the wrong order, reverse them.
    IF @StartDate > @EndDate
        SELECT @Swap      = @EndDate,
               @EndDate   = @StartDate,
               @StartDate = @Swap

    --Calculate and return the number of workdays using the input parameters.
    --This is the meat of the function.
    --This is really just one formula with a couple of parts that are listed on separate lines for documentation purposes.
    RETURN (
        SELECT
        --Start with total number of days including weekends
        (DATEDIFF(dd,@StartDate, @EndDate)+1)
        --Subtact 2 days for each full weekend
        -(DATEDIFF(wk,@StartDate, @EndDate)*2)
        --If StartDate is a Sunday, Subtract 1
        -(CASE WHEN DATENAME(dw, @StartDate) = 'Sunday'
            THEN 1
            ELSE 0
        END)
        --If EndDate is a Saturday, Subtract 1
        -(CASE WHEN DATENAME(dw, @EndDate) = 'Saturday'
            THEN 1
            ELSE 0
        END)
        --Subtract all holidays
        -(Select Count(*) from [DB04\DB04].[Gateway].[dbo].[tblHolidays]
          where  [HolDate] between @StartDate and @EndDate )
        )
    END  
GO
-- Test Script
/*
declare @EndDate datetime= dateadd(m,2,getdate())
print @EndDate
select  [Master].[dbo].[fn_WorkDays] (getdate(), @EndDate)
*/

My version of the accepted answer as a function using DATEPART, so I don't have to do a string comparison on the line with

DATENAME(dw, @StartDate) = 'Sunday'

Anyway, here's my business datediff function

SET ANSI_NULLS ON
GO
SET QUOTED_IDENTIFIER ON
GO

CREATE FUNCTION BDATEDIFF
(
    @startdate as DATETIME,
    @enddate as DATETIME
)
RETURNS INT
AS
BEGIN
    DECLARE @res int

SET @res = (DATEDIFF(dd, @startdate, @enddate) + 1)
    -(DATEDIFF(wk, @startdate, @enddate) * 2)
    -(CASE WHEN DATEPART(dw, @startdate) = 1 THEN 1 ELSE 0 END)
    -(CASE WHEN DATEPART(dw, @enddate) = 7 THEN 1 ELSE 0 END)

    RETURN @res
END
GO