I have a stored procedure which is being called from a dbms job. i.e.

DBMS_SCHEDULER.RUN_JOB ('Procedure_JB', FALSE);

A java code stored procedure, which after doing some stuff, kicks off Procedure_JB asynchronously. And then this Procedure_JB calls Procedure_PRogram and then the program would call the stored procedure.

How can i pass arguments to my stored procedure?

  • The arguments which i have to pass to the job are from java.
like image 305
Em Ae Avatar asked Feb 07 '12 16:02

Em Ae


2 Answers

Define your job Procedure_JB to accept arguments. Then use dbms_scheduler.set_job_argument_value to define the value of the arguments you want to pass into the program your job is going to run. An example (taken from https://forums.oracle.com/forums/thread.jspa?threadID=483135)

-- create a stored procedure with two arguments
create or replace procedure myproc (arg1 in varchar2, arg2 in varchar2)
is BEGIN null; END;
/

-- create a program with two arguments and define both
begin
dbms_scheduler.create_program
(
program_name=>'myprog',
program_action=>'myproc',
program_type=>'STORED_PROCEDURE',
number_of_arguments=>2, enabled=>FALSE
) ;

dbms_scheduler.DEFINE_PROGRAM_ARGUMENT(
program_name=>'myprog',
argument_position=>1,
argument_type=>'VARCHAR2',
DEFAULT_VALUE=>'13');

dbms_scheduler.DEFINE_PROGRAM_ARGUMENT(
program_name=>'myprog',
argument_position=>2,
argument_type=>'VARCHAR2');

dbms_scheduler.enable('myprog');
end;
/

-- create a job pointing to a program and set both argument values
begin
dbms_scheduler.create_job('myjob',program_name=>'myprog');
dbms_scheduler.set_job_argument_value('myjob',1,'first arg');
dbms_scheduler.set_job_argument_value('myjob',2,'second arg');
dbms_scheduler.enable('myjob');
end;
/
like image 194
Mike McAllister Avatar answered Sep 30 '22 18:09

Mike McAllister


Use PLSQL_BLOCK instead:

begin
dbms_scheduler.create_job (
    job_name => 'myjob',
    job_type => 'PLSQL_BLOCK',
    job_action => 'BEGIN myproc(''first arg'',''second arg''); END;',
    start_date => sysdate,
    repeat_interval => 'FREQ=HOURLY',
    enabled => true    
);
end;
/
like image 25
Steve G Avatar answered Sep 30 '22 16:09

Steve G