Merge node in activity diagram

I'm learning Activity diagram in UML and now I'm confused with the following diagram for representing procedures when calling a pizza.enter image description here

I think a merge node should be added before the join node because if not, the join node will wait forever. Is that correct? Thank you.

like image 905
lenhhoxung Avatar asked Sep 25 '22 19:09

lenhhoxung


1 Answers

I think you are right.

There should be a merge node merging the two flows coming from the decision right after Ask for toppings and a merge node to merge the two flows that have been split by the decision right after Deliver Pizza

A join node will only continue if it gets a token from all incoming flows, which will never happen if those flows are mutually exclusive because of a decision earlier on.

like image 86
Geert Bellekens Avatar answered Sep 29 '22 06:09

Geert Bellekens