I am attempting to test misfired tasks with APScheduler, but I am not seeing the missed tasks run when I restart APScheduler. I have configured APScheduler as follows:
scheduler.py
def configure_scheduler():
jobstores = {
'default': SQLAlchemyJobStore(url=config('DATABASE_URL'))
}
sched = BlockingScheduler()
sched.configure(jobstores=jobstores)
sched.add_job(
test_task,
id='test_task',
'interval',
hours=1,
coalesce=True,
max_instances=1,
misfire_grace_time=360,
replace_existing=True
)
return sched
if __name__ == '__main__':
scheduler = configure_scheduler()
scheduler.start()
When I start the scheduler the first time, test_task is added to the apscheduler_jobs table in my Postgres database with a next_run_time of one hour from when I start the scheduler. I then attempt to test a misfire by:
next_run_time in my database to the current timeWhen I follow this procedure, the next_run_time is again set to an hour from the current time. The next_run_time appears to be updated in the update_job method of the SQLAlchemy jobstore. I have seen one similar question related to persistent job store tasks not running after a misfire. The solution to most other questions I have seen is to add the misfire_grace_time argument to add_job. I have tried this per my configuration above but have not had any luck running missed jobs on scheduler startup. Am I missing something related to how the replace_existing and misfire_grace_time arguments interact? Do I need to manually check if the next_run_time of any jobs is in the past, then run these jobs before starting the scheduler?
I am using v3.6.1 of the APScheduler library.
For additional context, I will be deploying the scheduler on Heroku and I am attempting to work around Heroku's automatic dyno cycling which occurs at least once per day.
After some discussion on the APScheduler Gitter chat room with Alex Grönholm (the creator of APScheduler), I was able to determine that the job was being "overwritten" in my database because I have replace_existing=True in my call to add_job. This causes the scheduler to replace the job in the jobstore every time the scheduler starts.
My workaround
Before the scheduler starts, check the apscheduler_jobs table for existing jobs.
For each job in the database, check the next_run_time against the current time. If the next_run_time is in the past, run the job now.
Schedule the jobs as before, using replace_existing=True.
Start the scheduler.