I know that I must use this instead of java.util.Timer because of various reasons. So, to study this I was looking at the docs and I have a few questions:
scheduleWithFixedDelay() work ? My understanding is this: It first executes a task after a given delay. Once the task is done, it waits for the specified time and then executes the task again. scheduleAtFixedRate() that takes a lot more time to execute than the specified delay ? Like I want the task to execute every 5 seconds but it takes 10 seconds to complete. My understanding is that the task will be held in a queue and will be executed once a core thread is availablescheduleWithFixedDelay() and scheduleAtFixedRate() differ: scheduleWithFixedDelay() waits for the task to finish executing, waits for the specified time and then fires the task again where as scheduleAtFixedRate will just keep firing the task without caring if it has completed or not. Correct?Think of it this way: