How I have to convert Task.Duration that get valid result? I find explanations about this property in MSDN:

Gets or sets the duration (in minutes) of a task.

But it doesn't work correct.

If I divided result by 60 (minutes in hour) and 24(hours in day) I get incorrect result.

But if I divided by 20 and 24 all it's ok. And I don't understand why. I use C# on .Net 3.5 and Office Primary Interop Assemblies ( Microsoft.Office.Interop.MSProject for office 2010).

I use that code :

 void SetProperties(MSProject.Task o, string version)
 {
                Wbs = o.WBS.ToString();
                Name = o.Name.ToString();
                StartDate = (System.DateTime) o.Start;
                FinishDate = (System.DateTime)o.Finish;
                Iteration = version;
                duration = (Convert.ToInt16(o.Duration)/10/24).ToString();//after result //divided by 2 I get correct result. Why?
}

thanks

like image 274
Iva Avatar asked Mar 31 '26 17:03

Iva


1 Answers

The reason that it doesn't work like you expect is because in a day you do not have 24 hours of working time. The Duration of a task is the amount of working time between the start and finish, not the absolute number of hours.

Since the default number of working hours in a day is 8, you divide the total minutes by 480 (60 min * 8 hours) to get the number of days. Your calculation of 20 * 24 just so happens to also equal 480, so you stumbled upon the correct number.

Of course, do not expect that Start + Duration (in days) is going to equal your Finish date. That's because you also have to factor in non-working days, like weekends. So you can have a 3 day task that starts on Friday, and it will not finish until the end of the day on Tuesday (5 calendar days).

like image 111
patmortech Avatar answered Apr 03 '26 08:04

patmortech



Donate For Us

If you love us? You can donate to us via Paypal or buy me a coffee so we can maintain and grow! Thank you!