Calculate Date by number of working days from a certain Startdate

I've got two tables, a project table and a calendar table. The first containts a startdate and days required. The calendar table contains the usual date information, like date, dayofweek, and a column is workingday, which shows if the day is a saturday, sunday, or bank holiday (value = 0) or a regular workday (value = 1).

For a certain report I need write a stored procedure that calculates the predicted enddate by adding the number of estimated workddays needed.

Example:

**Projects**
Name         Start_Planned  Work_days_Required
Project A    02.05.2016     6

Calendar (04.05 is a bank holdiday)
Day          Weekday        Workingday
01.05.2016   7              0
02.05.2016   1              1    
03.05.2016   2              1
04.05.2016   3              0
05.05.2016   4              1
06.05.2016   5              1
07.05.2016   6              0
08.05.2016   7              0
09.05.2016   1              1
10.05.2016   2              1

Let's say, the estimated number of days required is given as 6 (which leads to the predicted enddate of 10.05.2016). Is it possible to join the tables in a way, which allows me to put something like

select date as enddate_predicted
from calendar
join projects
where number_of_days = 6

I would post some more code, but I'm quite stuck on how where to start.

Thanks!

like image 261
Mister 832 Avatar asked Dec 19 '25 05:12

Mister 832


2 Answers

You could get all working days after your first date, then apply ROW_NUMBER() to get the number of days for each date:

SELECT  Date, DayNum = ROW_NUMBER() OVER(ORDER BY Date)
FROM    Calendar
WHERE   IsWorkingDay = 1
AND     Date >= @StartPlanned

Then it would just be a case of filtering for the 6th day:

DECLARE @StartPlanned DATE = '20160502',
        @Days INT = 6;

SELECT  Date
FROM    (   SELECT  Date, DayNum = ROW_NUMBER() OVER(ORDER BY Date)
            FROM    Calendar
            WHERE   WorkingDay = 1
            AND     Date >= @StartPlanned
        ) AS c
WHERE   c.DayNum = @Days;

It's not part of the question, but for future proofing this is easier to acheive in SQL Server 2012+ with OFFSET/FETCH

DECLARE @StartPlanned DATE = '20160502',
        @Days INT = 6;

SELECT  Date
FROM    dbo.Calendar
WHERE   Date >= @StartPlanned
AND     WorkingDay = 1
ORDER BY Date
OFFSET (@Days - 1) ROWS FETCH NEXT 1 ROWS ONLY

ADDENDUM

I missed the part earlier about having another table, and the comment about putting it into a cursor has prompted me to amend my answer. I would add a new column to your calendar table called WorkingDayRank:

ALTER TABLE dbo.Calendar ADD WorkingDayRank INT NULL;
GO
UPDATE  c
SET     WorkingDayRank = wdr
FROM    (   SELECT  Date, wdr = ROW_NUMBER() OVER(ORDER BY Date)
            FROM    dbo.Calendar
            WHERE   WorkingDay = 1
        ) AS c;

This can be done on the fly, but you will get better performance with it stored as a value, then your query becomes:

SELECT  p.Name,
        p.Start_Planned,
        p.Work_days_Required,
        EndDate = c2.Date
FROM    Projects AS P
        INNER JOIN dbo.Calendar AS c1
            ON c1.Date = p.Start_Planned
        INNER JOIN dbo.Calendar AS c2
            ON c2.WorkingDayRank = c1.WorkingDayRank + p.Work_days_Required - 1;

This simply gets the working day rank of your start date, and finds the number of days ahead specified by the project by joining on WorkingDayRank (-1 because you want the end date inclusive of the range)

This will fail, if you ever plan to start your project on a non working day though, so a more robust solution might be:

SELECT  p.Name,
        p.Start_Planned,
        p.Work_days_Required,
        EndDate = c2.Date
FROM    Projects AS P
        CROSS APPLY
        (   SELECT  TOP 1 c1.Date, c1.WorkingDayRank
            FROM    dbo.Calendar AS c1
            WHERE   c1.Date >= p.Start_Planned
            AND     c1.WorkingDay = 1
            ORDER BY c1.Date
        ) AS c1
        INNER JOIN dbo.Calendar AS c2
            ON c2.WorkingDayRank = c1.WorkingDayRank + p.Work_days_Required - 1;

This uses CROSS APPLY to get the next working day on or after your project start date, then applies the same join as before.

like image 136
GarethD Avatar answered Dec 23 '25 11:12

GarethD


This query returns a table with a predicted enddate for each project

select name,min(day) as predicted_enddate from (
    select c.day,p.name from dbo.Calendar c
    join dbo.Calendar c2 on c.day>=c2.day
    join dbo.Projects p on p.start_planned<=c.day and p.start_planned<=c2.day
    group by c.day,p.work_days_required,p.name
    having sum(c2.workingday)=p.work_days_required
) a
group by name
like image 34
Eyal Shulman Avatar answered Dec 23 '25 12:12

Eyal Shulman